CONSTRUCTION PROGRESS

DeliveryQ1 2027
StatusStructural work in progress
Photos updatedJuillet 2026
July 2026 — stone cladding installation, Villa Gaïa
July 2026 — stone cladding installation, Villa Gaïa
July 2026 — Villa Gaïa
July 2026 — Villa Gaïa
June 2026 — stone cladding sample
June 2026 — stone cladding sample
July 2026 — laying of the 120 × 120 tiling, Villa Gaïa
July 2026 — laying of the 120 × 120 tiling, Villa Gaïa
April 2026 — Villa Gaïa weathertight
April 2026 — Villa Gaïa weathertight
April 2026 — Villa Gaïa weathertight
April 2026 — Villa Gaïa weathertight
April 2026 — Villa Gaïa weathertight
April 2026 — Villa Gaïa weathertight
April 2026 — Villa Gaïa weathertight
April 2026 — Villa Gaïa weathertight
April 2026 — Villa Gaïa weathertight
April 2026 — Villa Gaïa weathertight
April 2026 — Villa Gaïa weathertight
April 2026 — Villa Gaïa weathertight
March 2026 — completion of the structural work
March 2026 — completion of the structural work
March 2026 — completion of the structural work
March 2026 — completion of the structural work
March 2026 — completion of the structural work
March 2026 — completion of the structural work
March 2026 — completion of the structural work
March 2026 — completion of the structural work
March 2026 — pouring of the final floor slab, Villa 2
March 2026 — pouring of the final floor slab, Villa 2
March 2026 — pouring of the final floor slab, Villa 2
March 2026 — pouring of the final floor slab, Villa 2
March 2026 — pouring of the final floor slab, Villa 2
March 2026 — pouring of the final floor slab, Villa 2
March 2026 — pouring of the final floor slab, Villa 2
March 2026 — pouring of the final floor slab, Villa 2
March 2026 — pouring of the final floor slab, Villa 2
March 2026 — pouring of the final floor slab, Villa 2
March 2026 — pouring of the final floor slab, Villa 2
March 2026 — pouring of the final floor slab, Villa 2
March 2026
March 2026
March 2026
March 2026
February 2026
February 2026
February 2026
February 2026
February 2026
February 2026
February 2026
February 2026
February 2026
February 2026
February 2026
February 2026
February 2026
February 2026
February 2026
February 2026
January 2026 — ground-floor slab, Villa Gaïa
January 2026 — ground-floor slab, Villa Gaïa
January 2026 — ground-floor slab, Villa Gaïa
January 2026 — ground-floor slab, Villa Gaïa
January 2026 — formwork for the first-floor lower slab, Villa Hélios
January 2026 — formwork for the first-floor lower slab, Villa Hélios
January 2026 — formwork for the first-floor lower slab, Villa Hélios
January 2026 — formwork for the first-floor lower slab, Villa Hélios
January 2026 — formwork for the first-floor lower slab, Villa Hélios
January 2026 — formwork for the first-floor lower slab, Villa Hélios
January 2026 — ground-floor slab in progress, Villa Gaïa
January 2026 — ground-floor slab in progress, Villa Gaïa
January 2026 — formwork for the ground-floor ceiling slab, Villa Hélios
January 2026 — formwork for the ground-floor ceiling slab, Villa Hélios
January 2026 — formwork for the ground-floor ceiling slab, Villa Hélios
January 2026 — formwork for the ground-floor ceiling slab, Villa Hélios
January 2026 — formwork for the ground-floor ceiling slab, Villa Hélios
January 2026 — formwork for the ground-floor ceiling slab, Villa Hélios
January 2026 — formwork for the ground-floor ceiling slab, Villa Hélios
January 2026 — formwork for the ground-floor ceiling slab, Villa Hélios
December 2025 — raising of the ground-floor walls, Villa Hélios
December 2025 — raising of the ground-floor walls, Villa Hélios
December 2025 — raising of the ground-floor walls, Villa Hélios
December 2025 — raising of the ground-floor walls, Villa Hélios
December 2025 — structural work in progress
December 2025 — structural work in progress
December 2025 — structural work in progress
December 2025 — structural work in progress
December 2025 — completion of the lower slab, Villa Hélios
December 2025 — completion of the lower slab, Villa Hélios
December 2025 — completion of the lower slab, Villa Hélios
December 2025 — completion of the lower slab, Villa Hélios
December 2025 — floor slab construction
December 2025 — floor slab construction
December 2025 — construction of a wine cellar
December 2025 — construction of a wine cellar
November 2025 — structural work
November 2025 — structural work
November 2025 — structural work
November 2025 — structural work
November 2025 — structural work
November 2025 — structural work
November 2025 — structural work
November 2025 — structural work
November 2025 — structural work
November 2025 — structural work
November 2025 — structural work
November 2025 — structural work
September – October 2025 — earthworks in progress
September – October 2025 — earthworks in progress
September – October 2025 — earthworks in progress
September – October 2025 — earthworks in progress
September – October 2025 — earthworks in progress
September – October 2025 — earthworks in progress
September – October 2025 — earthworks in progress
September – October 2025 — earthworks in progress
September – October 2025 — earthworks in progress
September – October 2025 — earthworks in progress
September – October 2025 — earthworks in progress
September – October 2025 — earthworks in progress
September – October 2025 — earthworks in progress
September – October 2025 — earthworks in progress
September – October 2025 — earthworks in progress
September – October 2025 — earthworks in progress
September – October 2025 — earthworks in progress
September – October 2025 — earthworks in progress
September – October 2025 — earthworks in progress
September – October 2025 — earthworks in progress
July 2025 — garage demolition
July 2025 — garage demolition
June 2025 — pruning of the vegetation
June 2025 — pruning of the vegetation